Project Overview

Completed in November of 2020, Veit performed the complete site work package for a new Kroger Fulfilment Center in Pleasant Prairie, WI. Construction of this 337,000SF facility included the excavation for the foundations, excavation and grading of a 19-acre retention pond, grading for parking lots and drives, and finally, all underground utilities. Our crews installed a staggering 17,000’ of sanitary sewer alone, as well as the complete storm drain and waterline systems. 

Market
Commercial
Owner
Kroger
Type of Project
Earthwork, Utility
Project Scope
Excavation; Deep Hole Excavation; Foundation; Wet and Dry Utilities
Duration
April 2020 - December 2020
Veit employee in heavy equipment
Your crew is a fantastic representation of Veit. Please commend these gentlemen for the awesome work they do. It’s obvious that they care about and enjoy working for you. Thanks for your time and Veit’s professionalism.
Welsh Construction, LLC Christian Mowery

Challenges We Solved

01.
Soil Remediation
A significant challenge on this site were the unsuitable soils that needed to be managed. Our soil remediation crew performed cement stabilization on all structural areas that required it. The general contractor on this project required that any soils stabilized with cement had to be set to finish grade and compacted within 90 minutes of application. This meant our crews had to ensure proper planning and execution to avoid any rework.
02.
Sanitary Sewer Installation
Because of the 17,000 feet of pipe needed, we took additional time in the preconstruction phase to plan each step of the installation in order to keep the project moving seamlessly and without interruption.